Significant progress has been made over the past month at The First Building of Bradfield City Centre, home to the Advanced Manufacturing Research Facility. September saw multiple milestones as we successfully poured the office slab, the manufacturing halls’ columns, and the south wall, further reinforcing the project’s structural integrity. The team is currently preparing the plinths for the structural steel column pour. Concurrently, the excavation of the site’s entrance roads is underway, with ongoing compaction of the fill material.
The arrival of structural steel on-site this week is a pivotal moment on our project timeline, which will be closely followed by the pouring of the manufacturing hall ground floor slab, leaving only the central spine slab on the horizon.